Nate and I make a weekly trip to our house to see the progress. Nate's siblings make fun of us but it is really exciting for us to see the changes being made and letting us know we are one step closer to having a place to call ours. Since I last updated alot has changed.......

Drywall is up prepping for paint













Paint is done although not up to my dad's opinion (he is a professional painter).

Tile installed



Cabinets installed



Doors Installed






Lights installed






Our tubs and shower are installed




Railing Installed




Our Countertops were installed today. I went there to take a picture of the outside and the countertops were being installed.It was a nice surprise since I didn't think they would be until later this week.






The beginnings of the exterior is started, they should be done with the stucco this week and start on the rock by the end of the week.


After that we have the finish work, carpet and hardwood floors to be installed, and pouring our driveway (this may be tricky as they need 72 hours straight of no moisture to make sure the cement dries correctly. If not we will end up with cracks or they will delay our closing date.)

Our estimated close date is March 18th so a month from today. Lets hope that is the date we get to move in.

Until the next update on our house........